The record

LegislationLegislation· Dec 2025
HR 3616 Passed House — in Senate

Sponsored by Troy Balderson (R)

Reliable Power Act

Requires federal agencies to get FERC approval before finalizing power-plant regulations during electricity shortages.

Tradeoff

Gives FERC a veto over environmental and energy agency rules affecting power plants when the grid faces supply shortages. Agencies must submit rules early and respond in writing to FERC's objections before finalizing them.

What's in it

See official bill text

Less than $500,000 net deficit impact over 2025-2035, with negligible effect after accounting for fee offsets.

The $1 million in federal spending is just the cost for agencies to run the review process itself; the real policy impact falls on electric utilities and grid operators who may face higher fees if FERC and the Electric Reliability Organization pass along their increased compliance costs, though CBO estimates these incremental fees would be small.

H.R. 3616, Reliable Power Act · Aug 2025

The House passed this 225-203 on December 17, 2025. The bill is now in the Senate.

  1. House

    Introduced

    (May 29, 2025)

  2. House

    Committee on Energy and Commerce(May 29, 2025)

  3. House

    The Committee on Energy and Commerce voted to send it to the floor

    Reported 28 - 23(Jun 25, 2025)

    Committee report H. Rept. 119-302.

  4. House

    Passage of the bill

    Passed(Roll #347 · Dec 17, 2025)

    225 yeanay 203
  5. Senate

    Received from the House

    on Energy and Natural Resources(Dec 18, 2025)

Passage votes so far· Dec 17, 2025· 119th Congress · 2025–2027